Building a villa in Geneva
Building a villa means running a multi-year project with a dozen parties. The main risk is not technical: it sits in decisions taken too early, without challenge.
Three ways to build, three risk profiles
- Architect with separate trades: maximum control, heavy coordination load
- Turnkey contractor: one contact for design and execution, but the same party sets the price and judges the work
- General contractor: global price and schedule, with the specification as the only reference
The real budget
The construction price is not the project cost. Studies, taxes, connections, landscaping, insurance and contingencies come on top. A budget with no contingency almost always ends in trade-offs during the works.
The schedule and its blocking points
Building permit, site release, contractor lead times, utility connections: every step has its own duration and dependencies. We hold a realistic schedule with the necessary margins, and flag drift before it accumulates.
Site control
- Regular visits and written minutes
- Compliance checks against plans and specification
- Invoice verification before payment
- Preparation of the handover and follow-up of reservations
Typical case
An owner accepted a general contractor's quote without a detailed finishes specification. Three months before delivery, finish selections generated a series of variations. Framing the scope upstream would have fixed those items in the contract.
Frequently asked
Questions owners ask us
A general contractor simplifies coordination but concentrates negotiating power on one side. Separate trades give more control, provided there is solid management. The right choice depends on your availability and your appetite for risk.
Owner's representation and construction management start at CHF 8,000 for an investment of CHF 800K to 5M. The amount depends on the delivery model and the length of the works.
In some cases, yes, depending on the municipality and the project. But design and execution control are two different professions: if nobody checks for you, the risk sits entirely with you.
Timelines vary with the municipality, the zone and the complexity of the file. We build them into the schedule from the start rather than discovering them on the way.