Handover and schedule of defects · Genève

Handover and schedule of defects (SIA 118)

Handover is the moment the risk changes hands. Poorly prepared, it turns fixable defects into a dispute. Done properly, it puts in writing what must be redone, by whom, and by when.

What handover commits you to

By accepting the works, the owner recognises that they comply, except for the defects listed. Anything not recorded that day becomes much harder to assert later. SIA 118 governs this step when the contract refers to it.

Preparing the inspection

  • Gathering plans, specification, variations and site minutes
  • Checking contractor documents and certificates
  • Preparing a checklist by room and by trade
  • Planning the necessary tests: heating, ventilation, plumbing, electrical

During the inspection

Each defect is recorded, photographed and located. We separate visible defects, which must appear in the minutes, from what belongs to use or future maintenance. Reservations are worded precisely enough to be verifiable.

After handover

The minutes are issued, reservations are tracked and their clearing is checked. Warranties run from handover: you need to know what they cover and how to activate them.

Typical case

At a handover, a terrace waterproofing defect had been mentioned verbally but not written into the minutes. After the first rainy season, the repair was disputed. A written reservation would have been enough.

Frequently asked

Questions owners ask us

A total refusal requires defects of particular gravity. In most cases handover is pronounced with reservations, which protects your rights while letting the project continue.

It is a defect recorded on the day of handover and written into the minutes, which the contractor undertakes to correct. A poorly worded reservation is hard to enforce: it must describe the defect, its location and, where possible, the expected deadline.

The minutes are drawn up at handover and signed by the parties. We prepare them with you and check that every point raised is included before signature.

Deadlines are set by the contract and by law, and depend on the nature of the defect. We check the framework that applies to your file and track the deadlines.

A 30-minute call is enough to assess your situation.