Delivery delay of a new apartment in Switzerland: what are your rights?

Delivery delay of a new apartment in Switzerland: what are your rights?

Purchasing a new off-plan apartment in Geneva is a major milestone. However, this excitement can quickly fade if the handover date slips by weeks or even months. A delivery delay in Switzerland is a contractual situation that requires a structured response to protect your interests.

As an Assistant to the Project Owner (AMO), KERLINE SA helps you anticipate these risks. Here are the key points to understand your rights and take effective action.

Understanding the legal framework: Code of Obligations vs. SIA 118 Standard

In Switzerland, deadline management relies on two main pillars. The Code of Obligations (CO) sets the general legal framework, while the SIA 118 standard—if integrated into the contract—provides crucial details for construction site management.

It is common to assume that a construction schedule is set in stone. However, legally, meeting deadlines depends on the nature of your contract: it is crucial to verify whether the schedule was purely indicative or a firm contractual commitment.

Note that delays are not always the contractor's fault. Issues with material delivery, exceptional weather, or delays by the owner in selecting finishes can sometimes justify an extension of the deadlines.

Delivery delays: What are your options?

If the scheduled delivery date has passed, your strategy depends on the applicable contractual regime:

  • Notice of default: If the contract does not specify a mandatory date, you must formally notify the contractor via registered mail, granting a reasonable additional period to complete the work.
  • Penalty clauses: These are not automatic and must be explicitly stipulated in your contract. Without an explicit penalty clause, it is often difficult to obtain compensation without proving direct, tangible financial loss.
  • Rights after the grace period: If the additional period expires with no results, the Code of Obligations allows you to demand forced execution, claim damages for non-performance, or terminate the contract.

The preventive role of the AMO

The best defense is anticipation. At KERLINE SA, we intervene from the moment the contract is signed to check the robustness of delay-related clauses. A well-drafted contract includes precise milestones and deterrent penalties.

Throughout the construction process, our role is to maintain constructive pressure on all parties. We monitor the actual progress of the site against the theoretical schedule to detect any slippage before it becomes irrecoverable.

Conclusion

When faced with a delay, do not remain passive. Lack of formal action can weaken your future recourse. To explore these issues further, we invite you to consult the analyses in the OAKS journal, a reference for the Swiss real estate market.

KERLINE SA stands by Geneva buyers to secure their projects. As an independent AMO, we represent only your interests. Our expertise allows us to navigate the nuances of the CO and the SIA standard to ensure your investment succeeds.

Further reading

In the OAKS journal

Need expert guidance?

Let's discuss your project in 30 minutes.

Contact us
This site uses cookies essential to its operation and an anonymous audience measurement, enabled only if you accept. No advertising cookies are used. Privacy Policy