Delay in the delivery of a new apartment in Switzerland: what are your rights?

Delay in the delivery of a new apartment in Switzerland: what are your rights?

Buying a property off-plan is an exciting venture, but it comes with its share of uncertainties. For many buyers in Geneva and French-speaking Switzerland, the announcement of a delay in the handover date is a source of intense stress.

Between temporary housing costs, bridging loans, and logistical planning, a long-drawn-out construction site has tangible impacts on your life. Understanding your rights and the legal levers at your disposal is essential to react calmly to a delivery delay.

Distinguishing between projected date and contractual date

The first step, often overlooked, is to analyze your sales contract. It is crucial to distinguish between a "projected date" and a binding contractual date.

If your contract mentions a simple estimate, the developer has more leeway. However, if a specific delivery date has been set, the contractor is obliged to comply with it.

In Switzerland, if no date is explicitly set, the contractor is obliged to deliver the work within a timeframe consistent with the nature of the project. However, never let ambiguity persist: without a firm date, your ability to claim penalties is significantly reduced.

The legal framework: Code of Obligations and SIA 118 Standard

Swiss construction law is based primarily on the Code of Obligations (CO) and, if integrated into your contract, the SIA 118 standard.

  • The Code of Obligations (art. 102 et seq., 366 CO): If the contractor does not respect the deadline, they are in default. You have the right to demand the completion of the work and claim damages for the prejudice suffered.
  • SIA 118 Standard: It offers a more structured framework requiring the contractor to take all reasonable measures to meet deadlines (art. 95). Note, however, that late-delivery penalties are not automatic and must be specifically provided for and quantified in your contract.

The formal notice procedure: do not waste time

As soon as the delay becomes effective or is seriously foreseeable, do not wait for the deadline.

  • Send a formal registered letter to the general contractor or developer.
  • Set a reasonable additional grace period for delivery. This formal notice is essential to assert your rights later.
  • Document every exchange and keep a written record of all communications regarding the construction schedule.

Your levers of action against the delay

If the delay persists despite your reminders, several options are available to you:

  • Late-delivery penalties: If a penalty clause is included in your contract, it must be applied, usually calculated per day of delay.
  • Claims for damages: If you suffer actual financial prejudice with proven additional costs, you can claim compensation.
  • The right to terminate the contract: In extreme cases, Article 366 para. 1 CO allows, under strict conditions, the termination of the contract.

How KERLINE SA protects you

At KERLINE SA, we believe that the best defense against delivery delays is anticipation. As a Geneva-based Project Management Assistance (AMO) firm, we act exclusively for you, the buyer.

We intervene well before signing to audit contractual clauses. Throughout the construction period, our experts conduct regular visits to monitor actual progress and steer the necessary steps to hold the contractor accountable.